{"id":2433,"date":"2026-09-09T13:45:23","date_gmt":"2026-09-09T18:45:23","guid":{"rendered":"https:\/\/schondube.com\/en\/?page_id=2433"},"modified":"2026-09-09T13:46:20","modified_gmt":"2026-09-09T18:46:20","slug":"golf-course-marina-environmental-permits-mexico","status":"publish","type":"page","link":"https:\/\/schondube.com\/en\/environmental-and-urban-law\/environmental-impact-authorization-mexico\/golf-course-marina-environmental-permits-mexico\/","title":{"rendered":"Golf course and Marina environmental permits in Mexico"},"content":{"rendered":"\n<p class=\"wp-block-paragraph\">Golf courses and marinas are two of the most scrutinized development categories in Mexico&#8217;s coastal zones. They are not scrutinized because they are singled out arbitrarily. They are scrutinized because they combine large land footprints, significant water consumption, proximity to sensitive coastal ecosystems, and impacts on the federal maritime zone\u2014the precise combination of factors that Mexico&#8217;s environmental regulatory framework was designed to address. Foreign investors entering either category without understanding the permit stack and the realistic timeline tend to find out how long the process actually takes the expensive way.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Golf courses: the environmental review challenge<\/strong><\/h2>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Why golf triggers MIA regional<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Golf course projects in Mexico almost universally require a MIA Regional rather than the standard MIA Particular. The regional modality is triggered when a project affects multiple ecosystems, involves large land areas, or has cross-jurisdictional impacts. Golf courses in Quintana Roo typically meet all three criteria: an 18-hole course covers 60 to 80 hectares, typically crosses multiple vegetation community types, affects drainage patterns across a significant area, and involves water consumption that draws from the regional aquifer system.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The MIA Regional requires a more extensive baseline study, broader impact modeling, and typically involves more SEMARNAT technical committee engagement. It also takes longer to resolve.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Water use authorization from CONAGUA<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">The most significant single permit challenge for a golf course in the Yucatan Peninsula is not the MIA\u2014it is the CONAGUA water concession for aquifer extraction.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The Yucatan Peninsula has no surface rivers. All freshwater is stored in the karst limestone aquifer system beneath the surface, accessible through cenotes, caves, and extraction wells. The aquifer feeds the cenotes that connect to the coastal zone and ultimately to the Caribbean. A golf course in Quintana Roo may require 500,000 to 2,000,000 cubic meters of water per year for irrigation, depending on size, turf species, climate, and efficiency technology. Every cubic meter must come from CONAGUA-authorized extraction.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">CONAGUA grants water concessions (t\u00edtulos de concesi\u00f3n de aguas nacionales) for specific volumes of extraction from defined aquifer zones. The concession application must demonstrate that the requested volume does not exceed the sustainable yield of the aquifer in the relevant administrative unit. In areas where the aquifer is already heavily subscribed\u2014which describes most of the northern Quintana Roo coast\u2014obtaining a new concession for large-volume extraction is not automatic, and CONAGUA may impose volume restrictions or conditions.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">SEMARNAT&#8217;s review of the golf course MIA will look closely at the water balance: how much water will the course use, where will it come from, what is the impact on the aquifer and on the cenote systems that connect to it, and what efficiency measures will reduce consumption. Recycled wastewater for irrigation\u2014using treated effluent from the resort or municipality rather than fresh aquifer water\u2014is a condition SEMARNAT commonly imposes and that can significantly reduce the volume of fresh groundwater concession required.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Best management practices as MIA conditions<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">SEMARNAT typically attaches a set of best management practice conditions to golf course approvals. These vary by project but commonly include the following:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Integrated pest management (IPM) programs that minimize pesticide use and specify approved chemical inputs<\/li>\n\n\n\n<li>Buffer zones between the course and sensitive habitats\u2014cenotes, wetlands, mangroves\u2014with defined minimum setbacks and restrictions on pesticide application within the buffer<\/li>\n\n\n\n<li>Soil management plans to prevent erosion and minimize sediment loading into karst drainage features<\/li>\n\n\n\n<li>Turf species selection conditions\u2014grass varieties with lower water and chemical requirements<\/li>\n\n\n\n<li>Monitoring programs for groundwater quality near the course<\/li>\n\n\n\n<li>Annual reporting to SEMARNAT on water consumption, pesticide use, and monitoring results<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">These are not suggestions. They are legal conditions of the authorization. PROFEPA enforces them through inspections, and a golf course that cannot document compliance with its MIA conditions is a course with an enforcement exposure.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Marinas: stacking federal permits on top of each other<\/strong><\/h2>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>ZOFEMAT concession from SEMARNAT<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">A marina by definition occupies the Zona Federal Mar\u00edtimo-Terrestre (ZOFEMAT) and typically the adjacent federal protection zone as well. The marina&#8217;s dock infrastructure, boat slips, breakwaters, and access facilities are within the 20-meter federal zone measured from the high tide line or within the water column of navigable waterways that are also federal domain.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The first federal permit requirement for a marina is a ZOFEMAT concession from SEMARNAT authorizing the occupation of the federal maritime zone. The concession application requires a certified ZOFEMAT survey establishing the boundary, an environmental opinion (dictamen ambiental) addressing impacts of the marina on coastal ecosystems, a detailed project description with dimensions of all structures, and documentation establishing the applicant&#8217;s legal standing with respect to the adjacent land.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">ZOFEMAT concessions for marinas are typically granted for 20 years and carry annual fee obligations under the Ley Federal de Derechos based on the square meters of federal zone occupied and the zone&#8217;s commercial category. In tourist zones of Quintana Roo, these fees are substantial.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>MIA authorization<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">The marina also requires a separate MIA authorization under LGEEPA Article 28. The marina MIA will address dredging impacts, construction of fixed structures in the coastal zone, modifications to coastal geomorphology, impacts on marine ecosystems including seagrass beds and reef structures, water quality changes from boat traffic and marina operations, and any upland development associated with the marina facility.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">For marinas near protected areas\u2014which describes most of the Quintana Roo coast, given the Mesoamerican Barrier Reef, the Sian Ka&#8217;an Biosphere Reserve to the south of Tulum, and numerous smaller protected areas\u2014CONANP will be formally consulted during the MIA review. If the marina is within or adjacent to a natural protected area, the CONANP consultation is mandatory and typically extends the review timeline.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Additional federal permits<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Beyond the ZOFEMAT concession and the MIA, a marina requires:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Capitan\u00eda de Puerto authorization.<\/strong> The Secretar\u00eda de Marina (SEMAR) and the port captaincy (Capitan\u00eda de Puerto) must authorize the marina as a port facility. This permit governs navigation safety, the channel layout, and boat access and egress. The capitan\u00eda review is parallel to the SEMARNAT process, not sequential, so it can run concurrently.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>SICT construction permit.<\/strong> Infrastructure that affects federal zone communications\u2014roads, utilities crossings, and coastal structures\u2014may require permits from the Secretar\u00eda de Infraestructura, Comunicaciones y Transportes (SICT).<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Dredging permit.<\/strong> Any dredging operation\u2014to create the marina basin, deepen the access channel, or remove sediment\u2014requires a separate permit that specifically authorizes the dredging activity, the disposal of dredged material, and controls to prevent turbidity and sediment resuspension from affecting reef or seagrass areas.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>CONAGUA authorization.<\/strong> If the marina includes any connection to inland waterways or lagoon systems, CONAGUA&#8217;s authorization for the hydrological modification may be required.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Environmental monitoring obligations for marinas<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">A marina&#8217;s operational MIA conditions typically include the following:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Water quality monitoring in the marina basin and adjacent coastal waters, with specific parameters (dissolved oxygen, turbidity, coliform bacteria, hydrocarbons) and monitoring frequency<\/li>\n\n\n\n<li>Sediment quality monitoring in the marina basin<\/li>\n\n\n\n<li>Oil and fuel spill prevention and response plan<\/li>\n\n\n\n<li>Sewage management plan for boats using the marina (no discharge requirements)<\/li>\n\n\n\n<li>Annual reporting to SEMARNAT<\/li>\n<\/ul>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>CONANP overlap near whale migration routes<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Several areas of Quintana Roo&#8217;s Caribbean coast sit within, or adjacent to, zones where whale sharks aggregate seasonally or where whale migration routes pass. If a proposed marina is in proximity to areas that CONANP has identified as critical habitat, CONANP&#8217;s consultation during the MIA review will address the potential disturbance from boat traffic. In some cases, CONANP conditions may impose seasonal navigation restrictions in the marina&#8217;s approach channels.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>The realistic timeline for a marina project<\/strong><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Investors who have developed marinas in Florida, the Caribbean, or elsewhere often enter the Mexican permit process with a 12 to 18-month timeline in mind. The actual experience for a marina project in a sensitive coastal zone in Quintana Roo\u2014where all federal permits must be obtained in parallel and CONANP is involved\u2014runs 2 to 4 years from permit application submission to construction authorization. Some projects have taken longer.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The factors that extend timelines: public consultation periods when required, CONANP consultations that generate conditions requiring project modifications, MIA information requests (prevenciones) that require supplemental studies, sequential processing of permits that could have been run in parallel, and marina designs that must be modified to address agency concerns.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The investors who move fastest are the ones who begin the permit process early\u2014before making final financing commitments\u2014and who have legal and environmental teams that manage all the permit tracks simultaneously rather than handling them in sequence.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">For detailed guidance on the MIA process that underlies these permit requirements, see our article on <a href=\"https:\/\/schondube.com\/en\/environmental-and-urban-law\/environmental-impact-authorization-mexico\/\">Environmental impact authorization (MIA) in Mexico<\/a>. For the full scope of our environmental legal services, visit our Environmental and Urban Planning Law practice page.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Frequently asked questions about golf course and marina permits in Mexico<\/strong><\/h2>\n\n\n\n<div data-wp-context=\"{ &quot;autoclose&quot;: false, &quot;accordionItems&quot;: [] }\" data-wp-interactive=\"core\/accordion\" role=\"group\" class=\"wp-block-accordion is-layout-flow wp-block-accordion-is-layout-flow\">\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-1&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading has-icon has-icon-right\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-1-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-1\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>Can a golf course use a private cenote on the property for irrigation instead of drilling new wells?<\/strong><br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-1\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-1-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">Using a cenote for water extraction requires a CONAGUA concession in the same way that drilling a well does. Cenotes are part of the national water system (aguas nacionales) under the Ley de Aguas Nacionales, and their use requires federal authorization. The concession application process is the same as for a conventional extraction well. Additionally, the MIA for the golf course will need to specifically address the cenote as both a water source and an ecologically sensitive feature\u2014cenotes are often home to species that appear on the NOM-059-SEMARNAT-2010 protected species list.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-2&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading has-icon has-icon-right\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-2-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-2\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>Does a marina need a separate environmental permit if it is part of a larger hotel resort development that already has an MIA?<\/strong><br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-2\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-2-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">It depends on what the hotel&#8217;s MIA covered. If the marina was part of the original project description in the hotel&#8217;s MIA, and the MIA authorization includes the marina within its authorized scope, a separate MIA for the marina may not be required\u2014though a ZOFEMAT concession still is. If the marina is a subsequent addition not covered by the original authorization, it requires its own MIA and all applicable additional permits. This is one of the reasons why developers are advised to build the full intended development program into the initial MIA filing, even if construction will be phased.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-3&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading has-icon has-icon-right\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-3-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-3\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>What is the annual ZOFEMAT concession fee for a marina in Quintana Roo?<\/strong><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-3\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-3-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">The fee is established by the Ley Federal de Derechos and updated annually. It is calculated on the square meters of ZOFEMAT occupied multiplied by the applicable rate for the zone category. Tourist-zone rates in Quintana Roo\u2014which apply to marina facilities in the Canc\u00fan, Playa del Carmen, and Tulum corridors\u2014run approximately MXN 150 to MXN 400 per square meter per year for commercial\/tourist use. A marina occupying 5,000 square meters of ZOFEMAT would pay MXN 750,000 to MXN 2,000,000 per year in concession fees. These figures should be confirmed against the current Ley Federal de Derechos rates for the specific year.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-4&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading has-icon has-icon-right\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-4-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-4\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>Can marina construction begin before all federal permits are in hand?<\/strong><br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-4\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-4-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">No work that requires federal authorization\u2014dredging, construction in the ZOFEMAT, or construction that requires MIA authorization\u2014can begin before the applicable authorization is granted. Some upland site preparation work outside the federal zone and outside any MIA-required area might proceed before all permits are finalized, but this must be assessed carefully against the specific project. The common mistake is beginning site preparation in areas that are not clearly excluded from the MIA&#8217;s scope, which PROFEPA then treats as unauthorized construction.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-5&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading has-icon has-icon-right\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-5-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-5\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>How does PROFEPA enforce marina compliance during operations?<\/strong><br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-5\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-5-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">PROFEPA inspects operational marinas against their MIA conditions and their ZOFEMAT concession conditions. Typical inspection focus areas: water quality monitoring results and whether they show permit limit exceedances, oil and fuel handling facilities and whether there is evidence of unreported spills, sewage management for boats and whether the marina has adequate pump-out facilities, whether the constructed marina matches the authorized dimensions, and whether annual monitoring reports have been submitted to SEMARNAT on schedule. Marinas with large boat volumes and significant fuel operations in sensitive coastal areas are high-priority inspection targets.<br><\/p>\n<\/div>\n<\/div>\n<\/div>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Explore related environmental guidance<\/strong><\/p>\n\n\n\n<div class=\"wp-block-buttons is-layout-flex wp-block-buttons-is-layout-flex\">\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/schondube.com\/en\/environmental-and-urban-law\/environmental-impact-authorization-mexico\/\">Environmental impact authorization (MIA) in Mexico<\/a><\/div>\n\n\n\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/schondube.com\/en\/environmental-and-urban-law\/environmental-impact-authorization-mexico\/semarnat-environmental-authorization-process\/\">Complete process for SEMARNAT environmental authorization<\/a><\/div>\n\n\n\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/schondube.com\/en\/environmental-and-urban-law\/environmental-impact-authorization-mexico\/environmental-due-diligence-real-estate-mexico\/\">Environmental due diligence in real estate transactions<\/a><\/div>\n<\/div>\n","protected":false},"excerpt":{"rendered":"<p>Golf courses and marinas are two of the most scrutinized development categories in Mexico&#8217;s coastal zones. They are not scrutinized because they are singled out arbitrarily. They are scrutinized because they combine large land footprints, significant water consumption, proximity to sensitive coastal ecosystems, and impacts on the federal maritime zone\u2014the precise combination of factors that [&hellip;]<\/p>\n","protected":false},"author":14,"featured_media":2416,"parent":2415,"menu_order":0,"comment_status":"closed","ping_status":"closed","template":"child-ee-octopus.php","meta":{"_seopress_titles_title":"","_seopress_titles_desc":"Environmental permits for golf courses and marinas in Mexico, including MIA, water authorizations, SEMARNAT review and ZOFEMAT.","_seopress_robots_index":"","_seopress_robots_follow":"","_seopress_robots_imageindex":"","_seopress_robots_snippet":"","_seopress_robots_primary_cat":"","_seopress_robots_breadcrumbs":"","_seopress_robots_freeze_modified_date":"","_seopress_robots_custom_modified_date":"","_seopress_robots_canonical":"","_seopress_social_fb_title":"","_seopress_social_fb_desc":"","_seopress_social_fb_img":"","_seopress_social_fb_img_attachment_id":0,"_seopress_social_fb_img_width":0,"_seopress_social_fb_img_height":0,"_seopress_social_twitter_title":"","_seopress_social_twitter_desc":"","_seopress_social_twitter_img":"","_seopress_social_twitter_img_attachment_id":0,"_seopress_social_twitter_img_width":0,"_seopress_social_twitter_img_height":0,"_seopress_redirections_value":"","_seopress_redirections_enabled":"","_seopress_redirections_enabled_regex":"","_seopress_redirections_logged_status":"","_seopress_redirections_param":"","_seopress_redirections_type":0,"_seopress_analysis_target_kw":"","_seopress_news_disabled":"","_seopress_video_disabled":"","_seopress_video":[],"_seopress_pro_schemas_manual":[],"_seopress_pro_rich_snippets_disable_all":"","_seopress_pro_rich_snippets_disable":[],"_seopress_pro_schemas":[],"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"set","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"class_list":["post-2433","page","type-page","status-publish","has-post-thumbnail","hentry"],"permalink_manager":null,"_links":{"self":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2433","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/users\/14"}],"replies":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/comments?post=2433"}],"version-history":[{"count":1,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2433\/revisions"}],"predecessor-version":[{"id":2434,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2433\/revisions\/2434"}],"up":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2415"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/media\/2416"}],"wp:attachment":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/media?parent=2433"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}