{"id":2378,"date":"2026-08-28T14:53:16","date_gmt":"2026-08-28T19:53:16","guid":{"rendered":"https:\/\/schondube.com\/en\/?page_id=2378"},"modified":"2026-08-28T14:55:33","modified_gmt":"2026-08-28T19:55:33","slug":"construction-permit-hotels-quintana-roo","status":"publish","type":"page","link":"https:\/\/schondube.com\/en\/real-estate-law\/real-estate-development-permits-mexico\/construction-permit-hotels-quintana-roo\/","title":{"rendered":"Obtaining a construction permit for hotels in Quintana Roo"},"content":{"rendered":"\n<p class=\"wp-block-paragraph\">Hotel and resort development on the Mexican Caribbean coast involves one of the most complex regulatory permit sequences in Mexico. The combination of federal environmental requirements, maritime zone concessions, state ecological zoning, and municipal construction licensing creates a multi-agency authorization process that takes 12-24 months even for well-prepared developers. Misunderstanding the sequence\u2014or starting construction without required authorizations\u2014creates legal exposure that can halt projects mid-build.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Why hotel permitting in Quintana Roo is distinctive<\/strong><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Three factors make Quintana Roo&#8217;s hotel permit process more demanding than most other Mexican states:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">First, virtually all developable coastal land is within federal environmental protection zones. The coast is ecologically sensitive\u2014mangroves, reef ecosystems, and protected turtle nesting beaches create overlapping federal regulatory jurisdiction that does not exist in the same density in industrial or urban development contexts.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Second, the beachfront involves the ZOFEMAT (zona federal mar\u00edtimo terrestre)\u2014federal land that requires its own concession from SEMARNAT, separate from and prior to the construction authorization.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Third, the state has adopted distinct ecological zoning programs (POET\u2014Programas de Ordenamiento Ecol\u00f3gico del Territorio) for the Canc\u00fan hotel zone, the Riviera Maya corridor, and the Tulum area. Each has different density limits, height restrictions, and environmental conditions. What is permitted in the Canc\u00fan hotel zone may be prohibited at Tulum.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>The six-step permit sequence<\/strong><\/h2>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Step 1: SEMARNAT environmental impact authorization (MIA)<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">The Manifestaci\u00f3n de Impacto Ambiental (MIA) is the federal environmental impact assessment filed with the Secretar\u00eda de Medio Ambiente y Recursos Naturales (SEMARNAT). For hotel developments on the coast, this is typically a &#8220;particular&#8221; or &#8220;regional&#8221; MIA depending on the project scale and location.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The MIA must be prepared by qualified environmental professionals and include a project description and technical specifications, characterization of the existing environment (vegetation, fauna, hydrology, and soils), analysis of environmental impacts, mitigation measures, a monitoring plan, and an abandonment and restoration plan.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Preparation of a complete MIA file for a significant hotel project takes <strong>3-6 months<\/strong> before filing. SEMARNAT has a 60-business-day period to resolve the authorization once the file is accepted as complete, though complex projects routinely require additional information requests (requerimientos de informacion adicional) that restart the clock. Total SEMARNAT authorization time from filing a complete MIA to resolution: <strong>4-8 months<\/strong> in practice.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The MIA resolution may impose conditions (condicionantes) that must be observed during and after construction\u2014environmental monitoring, species protection measures, vegetation buffers, and waste management requirements. These conditions become binding obligations of the project.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Step 2: ZOFEMAT concession<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Beachfront hotel development typically requires a ZOFEMAT concession from SEMARNAT to use the 20-meter federal maritime zone for beach access, pools, palapas, or other infrastructure. The concession is separate from the construction authorization and must be obtained before any development within ZOFEMAT begins.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The concession application requires proof of legal possession of the adjacent private land, a detailed description of proposed ZOFEMAT use, an environmental assessment of the proposed use, and payment of applicable fees. Concessions are granted for specific terms (typically 5-20 years) and are renewable. They can be revoked for violations of their conditions.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Developers should not assume that proximity to the water implies the right to use the ZOFEMAT strip. Operating on the beach without a concession is a federal infraction with significant penalties, including removal of unauthorized structures.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Step 3: state ecological zoning compliance (POET)<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">The Programa de Ordenamiento Ecol\u00f3gico del Territorio establishes land use categories and development parameters for different areas of Quintana Roo. Before finalizing project design, confirm which POET applies to the specific location and what parameters apply:<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Canc\u00fan hotel zone:<\/strong> POET administered by SEDETUR (state tourism ministry). Density, height, and setback limits are relatively permissive for established hotel land. Confirm the specific unit (UAG\u2014unidad de gestion ambiental) for the parcel.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Riviera Maya corridor:<\/strong> Different POET with stricter ecological conditions in the corridor between Puerto Morelos and Tulum. Tulum&#8217;s POET is separate from the Riviera Maya corridor and imposes specific height limits and density restrictions driven by the proximity of the Sian Ka&#8217;an Biosphere Reserve.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Tulum:<\/strong> Subject to its own ordinance and has been the subject of significant regulatory tightening since 2022. Verify current zoning status specifically for Tulum projects\u2014regulations have changed and projects that were authorized under prior rules may face different conditions.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Design the project to comply with the applicable POET before incurring significant architectural investment. A project that exceeds POET density or height limits cannot receive a construction license regardless of other permits.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Step 4: municipal construction license<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">The municipal construction license (licencia de construcci\u00f3n) is issued by the relevant municipality:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Benito Ju\u00e1rez<\/strong> for Canc\u00fan and Puerto Morelos area<\/li>\n\n\n\n<li><strong>Solidaridad<\/strong> for Playa del Carmen, Tulum, and Akumal<\/li>\n\n\n\n<li><strong>Cozumel<\/strong> for the island<\/li>\n\n\n\n<li><strong>L\u00e1zaro C\u00e1rdenas<\/strong> for Puerto Morelos (which shifted from Benito Ju\u00e1rez jurisdiction in 2016)<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">The construction license application requires the SEMARNAT MIA authorization, the architectural plans stamped by a licensed Director Responsable de Obra (DRO), structural calculations, evidence of land use compliance with POET, proof of property rights, and payment of municipal fees.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The municipality will not issue a construction license without the SEMARNAT MIA. This sequencing is absolute\u2014do not attempt to obtain a construction license before the environmental authorization.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Municipal review time is typically <strong>30-60 business days<\/strong> once the complete file is submitted, though complex projects and periods of high application volume extend this timeline.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Step 5: fire safety and civil protection permits<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Before commencing construction and again before opening, the project requires civil protection and fire safety approvals from the state and municipal civil protection authorities. For hotel projects, this includes fire suppression system plans, emergency egress design, structural load calculations, and fire protection equipment specifications.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Some municipalities require civil protection approval before the construction license is finalized. Others require it as a pre-opening inspection. Confirm the sequence with your permit coordinator early in the process.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\"><strong>Step 6: SECTUR hotel classification before operations<\/strong><\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Before opening to guests, a hotel in Mexico must obtain its official star classification from the Secretar\u00eda de Turismo (SECTUR) or the state tourism ministry. The classification confirms the hotel meets the physical and service standards for its category. Without classification, operating as a hotel violates tourism regulations.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The SECTUR classification process requires the completion of construction, installation of all guest services, and an inspection. Processing time varies but is typically 30-60 days from application.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Timeline and expediente \u00fanico<\/strong><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">For a full hotel project from land acquisition to opening, the permit timeline is realistically <strong>12-24 months<\/strong> depending on project complexity, prior site conditions, and regulatory workload.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Some municipalities in Quintana Roo have implemented an expediente unico\u2014a single filing point that coordinates the submission of documents to multiple agencies simultaneously. This can reduce the overall timeline by eliminating some serial filing delays. Confirm with your project team whether the expediente unico system applies to your specific project location.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Hotel construction file: documents and parallel approvals<\/strong><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">For a hotel project, the municipal construction application is only one workstream. The core file commonly includes registered title, cadastral certificate, current property tax receipt, alignment and official number certificates, land-use evidence, topographic survey, descriptive report, structural and installation calculations, architectural plans, construction log, and electricity, water, and drainage feasibility.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The size and location of a hotel can trigger a state urban-congruence review or an urban-impact assessment. Coastal or vegetated sites may also require an environmental impact authorization, forest land-use change authorization, and ZOFEMAT concession. A registered construction professional must coordinate the technical responsibility required by the municipality. Once work ends, the completion or occupancy process and cadastral update should be treated as closing conditions for the construction phase, not postponed until the business is ready to open.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Frequently asked questions<\/strong><\/h2>\n\n\n\n<div data-wp-context=\"{ &quot;autoclose&quot;: false, &quot;accordionItems&quot;: [] }\" data-wp-interactive=\"core\/accordion\" role=\"group\" class=\"wp-block-accordion is-layout-flow wp-block-accordion-is-layout-flow\">\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-1&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-1-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-1\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>Can we start site preparation before receiving the SEMARNAT MIA?<\/strong>\u00a0<br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-1\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-1-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">No. Site preparation that involves clearing vegetation, grading, or any land modification in an environmentally sensitive coastal area without the MIA authorization is a federal environmental infraction under the LGEEPA. PROFEPA (the environmental enforcement agency) actively monitors coastal development. Unauthorized clearing has resulted in project halts, criminal charges, and significant restoration orders. Do not begin site work until the MIA is in hand.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-2&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-2-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-2\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>What happens if SEMARNAT denies the MIA?<\/strong>\u00a0<br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-2\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-2-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">A denial can be challenged through administrative recourse before SEMARNAT within 15 business days of the resolution. If the administrative challenge fails, further judicial challenge (amparo) before a federal court is available. Both processes add significant time and cost. The most effective approach is a well-prepared MIA that anticipates SEMARNAT&#8217;s concerns and addresses them proactively in the original filing.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-3&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-3-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-3\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>Is a ZOFEMAT concession transferable when we sell the hotel?<\/strong>\u00a0<br><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-3\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-3-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">ZOFEMAT concessions are generally not automatically transferable. The sale of the adjacent private property does not automatically transfer the concession\u2014the buyer must apply for concession assignment or a new concession. This is an important point for hotel M&amp;A due diligence. Confirm the concession status and transferability before acquiring a beachfront hotel that relies on ZOFEMAT access.<\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-4&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-4-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-4\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong>How do height limits in Tulum&#8217;s POET affect hotel design?<\/strong><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-4\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-4-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">Tulum&#8217;s POET restricts building height significantly more than the Canc\u00fan hotel zone. Many Tulum development areas are limited to three or four stories above ground, with some areas more restrictive. The exact limit depends on the unidad de gestion ambiental (ecological management unit) applicable to the specific parcel. Confirm the applicable height limit with your architect and permit consultant before investing in design drawings.<br><\/p>\n<\/div>\n<\/div>\n\n\n\n<div data-wp-class--is-open=\"state.isOpen\" data-wp-context=\"{ &quot;id&quot;: &quot;accordion-item-5&quot;, &quot;openByDefault&quot;: false }\" data-wp-init=\"callbacks.initAccordionItems\" data-wp-on-window--hashchange=\"callbacks.hashChange\" class=\"wp-block-accordion-item is-layout-flow wp-block-accordion-item-is-layout-flow\">\n<h3 class=\"wp-block-accordion-heading\"><button aria-expanded=\"false\" aria-controls=\"accordion-item-5-panel\" data-wp-bind--aria-expanded=\"state.isOpen\" data-wp-on--click=\"actions.toggle\" id=\"accordion-item-5\" type=\"button\" class=\"wp-block-accordion-heading__toggle\"><span class=\"wp-block-accordion-heading__toggle-title\"><strong><strong>Do we need a separate permit for the hotel pool, spa, or beach club?<\/strong><\/strong><\/span><span class=\"wp-block-accordion-heading__toggle-icon\" aria-hidden=\"true\">+<\/span><\/button><\/h3>\n\n\n\n<div aria-labelledby=\"accordion-item-5\" data-wp-bind--hidden=\"state.isHidden\" data-wp-on--beforematch=\"actions.handleBeforeMatch\" id=\"accordion-item-5-panel\" role=\"region\" class=\"wp-block-accordion-panel is-layout-flow wp-block-accordion-panel-is-layout-flow\">\n<p class=\"wp-block-paragraph\">Major amenities like pools, spa facilities, and restaurants are included in the main construction license and MIA if they are part of the original project. Amenities added after initial construction require a separate construction license modification and potentially a MIA modification if they represent a significant environmental impact change. Beach club operations within ZOFEMAT require the ZOFEMAT concession to specifically authorize those uses.<br><\/p>\n<\/div>\n<\/div>\n<\/div>\n\n\n\n<h2 class=\"wp-block-heading\">Explore condominium regulations<\/h2>\n\n\n\n<div class=\"wp-block-buttons is-vertical is-layout-flex wp-container-core-buttons-is-layout-2c90304e wp-block-buttons-is-layout-flex\">\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/schondube.com\/en\/real-estate-law\/real-estate-development-permits-mexico\/\">Guide to real estate development permits in Mexico<\/a><\/div>\n\n\n\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/schondube.com\/en\/real-estate-law\/real-estate-development-permits-mexico\/condominium-regime-mexico-law\/\">Condominium property regime in M\u00e9xico and its legal rules<\/a><\/div>\n\n\n\n<div class=\"wp-block-button\"><a class=\"wp-block-button__link wp-element-button\" href=\"https:\/\/schondube.com\/en\/real-estate-law\/real-estate-development-permits-mexico\/operation-license-commercial-quintana-roo\/\">Operating licenses for businesses in Quintana Roo<\/a><\/div>\n<\/div>\n\n\n\n<p class=\"wp-block-paragraph\"><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Hotel and resort development on the Mexican Caribbean coast involves one of the most complex regulatory permit sequences in Mexico. The combination of federal environmental requirements, maritime zone concessions, state ecological zoning, and municipal construction licensing creates a multi-agency authorization process that takes 12-24 months even for well-prepared developers. Misunderstanding the sequence\u2014or starting construction without [&hellip;]<\/p>\n","protected":false},"author":14,"featured_media":2375,"parent":2372,"menu_order":0,"comment_status":"closed","ping_status":"closed","template":"child-ee-octopus.php","meta":{"_seopress_titles_title":"","_seopress_titles_desc":"Hotel construction permits in Quintana Roo - environmental authorization, ZOFEMAT, municipal licenses, and regulatory process for resort development.","_seopress_robots_index":"","_seopress_robots_follow":"","_seopress_robots_imageindex":"","_seopress_robots_snippet":"","_seopress_robots_primary_cat":"","_seopress_robots_breadcrumbs":"","_seopress_robots_freeze_modified_date":"","_seopress_robots_custom_modified_date":"","_seopress_robots_canonical":"","_seopress_social_fb_title":"","_seopress_social_fb_desc":"","_seopress_social_fb_img":"","_seopress_social_fb_img_attachment_id":0,"_seopress_social_fb_img_width":0,"_seopress_social_fb_img_height":0,"_seopress_social_twitter_title":"","_seopress_social_twitter_desc":"","_seopress_social_twitter_img":"","_seopress_social_twitter_img_attachment_id":0,"_seopress_social_twitter_img_width":0,"_seopress_social_twitter_img_height":0,"_seopress_redirections_value":"","_seopress_redirections_enabled":"","_seopress_redirections_enabled_regex":"","_seopress_redirections_logged_status":"","_seopress_redirections_param":"","_seopress_redirections_type":0,"_seopress_analysis_target_kw":"","_seopress_news_disabled":"","_seopress_video_disabled":"","_seopress_video":[],"_seopress_pro_schemas_manual":[],"_seopress_pro_rich_snippets_disable_all":"","_seopress_pro_rich_snippets_disable":[],"_seopress_pro_schemas":[],"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"set","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"class_list":["post-2378","page","type-page","status-publish","has-post-thumbnail","hentry"],"permalink_manager":null,"_links":{"self":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2378","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/users\/14"}],"replies":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/comments?post=2378"}],"version-history":[{"count":3,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2378\/revisions"}],"predecessor-version":[{"id":2383,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2378\/revisions\/2383"}],"up":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/pages\/2372"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/media\/2375"}],"wp:attachment":[{"href":"https:\/\/schondube.com\/en\/wp-json\/wp\/v2\/media?parent=2378"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}